New Construction Chicago Under $55 Million
Project Name:
Chicago Botanic Garden – The Regenstein Learning Campus
Submitting Company:
Turner Construction
Category:
New Construction Chicago Under $55 Million
Project Info Sheet:
Chicago Botanic Garden – The Regenstein Learning Campus
Project Description
Quality of Construction
Quality of plant material and planting methodology was critical for a successful completion of landscaping work. The Garden staff were integrated into the QA/QC process early on in the project to ensure that the high level of workmanship they expected would be integrated into this portion of the work.
Impact on the Community
The Learning Campus advances the ability of the Garden to advance a key initiative, which is to further develop an appreciation amongst the public the role that plants play in a sustainable environment.
Safety Record
Project Name:
St. Bernard Ambulatory Care Center
Submitting Company:
Berglund Construction
Category:
New Construction Chicago Under $55 Million
Project Info Sheet:
St. Bernard Ambulatory Care Center
Project Description
Quality of Construction
- 100% material verification
- In wall sign off
- Above ceiling sign off
- All city inspections and manufacture inspections
In addition to the above mentioned items, Berlund and all MEP contractors utilized BIM to coordinate all MEP items before construction began and utilized trimble layouts.
Impact on the Community
Safety Record
Project Name:
Uhlich Children’s Advantage Network (UCAN) City Campus Phase I and II
Submitting Company:
Gilbane Building Company
Category:
New Construction Chicago Under $55 Million
Project Info Sheet:
Uhlich Children’s Advantage Network (UCAN) City Campus Phase I and II
Project Description
Gilbane provided construction management services for the 54,500 SF Diermeier Therapeutic Youth Home (Phase I); and new 31,200 SF John D. and Alexandra C. Nichols Center Program Services and Headquarters Building (Phase II) located on a seven-acre urban site.
The three-story Diermeier Therapeutic Youth Home includes 70 rooms organized into dormitories for youth that have experienced severe violence, trauma, neglect and abuse. Each dormitory features single-occupancy bedrooms, a living room, restrooms and study areas, all connected to resident staff offices. The building includes a central dining room, full-service commercial kitchen, multipurpose gymnasium and fitness room. Social worker and therapist offices are also located throughout the facility, with group rooms that focus on art, computer science, group counseling and education.
The 1,500 SF full-service institutional kitchen includes all the equipment and facilities necessary to properly receive and store food and prepare meals by UCAN’s full-time kitchen staff. Meals are served to the residents in the 1,200 SF communal dining area via a 300 SF servery, which includes coolers, warmers and plate and utensil storage. A walk-in cooler, walk-in freezer and kitchen manager’s office are also included to support the food service operations.
The new two-story Nichols Center building includes administrative, violence prevention program and training space. It also provides UCAN with space to host large numbers of staff and/or external partners in one room for events such as trainings and workshops. The space is also available for community residents and organizations.
Quality of Construction
Lean construction practices combined with Gilbane’s Quality In Construction (QIC) program enhanced construction quality and minimized waste and rework on the UCAN City Campus.
Enhanced planning and visual communication tools identified the flow of work and a reliable schedule to optimize the execution of the work. Our QIC program ensured that the right work was being installed and satisfied or exceeded the scope requirements. This was achieved through mock-ups, first-delivery inspection, pre-installation meetings, rolling-completion inspections, quality inspections and daily huddles.
In addition, maximizing technology played a vital role in enhancing quality. The project utilized Building Information Modeling to coordinate above ceiling MEP/FP installation to eliminate conflicts and rework in the field. Bluebeam was utilized to manage the contract documents and posting of the documents was completed in real-time. This enabled the trade contractors to access the drawings in the field on lap-tops or tablets and provided current design documentation.
Impact on the Community
From the very beginning, Gilbane was committed to helping reinvest the funding for the UCAN project into local businesses and labor, and we valued and understood that building this facility was a major economic opportunity for the North Lawndale neighborhood, businesses and community.
Community relations and development was a top priority for this project with a 50% city of Chicago residency requirement and 28% DBE participation (24% MBE and 4% WBE). UCAN was not satisfied with just meeting these MBE/WBE requirements, so they set the project goal at 50% DBE participation (45% MBE and 5% WBE).
- Phase 1 – Reached: 63% (MBE participation: 47%, WBE participation: 16%)
- Phase II – Reached: 42% (MBE Participation: 37%, WBE Participation: 5%)
The new campus provides a community-based benefit on an unsafe parcel of land that had been vacant for more than 40 years, as well as closing an unsafe, hazardous street. The project has also delivered shared community space that includes prospects for a community garden, recreation area and sculpture garden.
Having the building in the community that it serves is of the utmost most importance to UCAN. Building the facility here was an extraordinary community development effort to encourage reinvestment in a struggling community; and to provide clinical services, support and mentoring to young people that need to heal, grow and thrive in their community.
Safety Record
Gilbane’s extensive and thorough safety program addresses the many aspects of safety. It integrates management philosophy and action, quality, regulatory and monetary requirements, as well as meeting the ultimate objective of successful project completion.
In order to proactively monitor and track safety performance in the field, Gilbane’s safety manager and project team performed regular safety inspections using SafetyNet, a software-based service on a tablet which allowed the team to instantly record safety-related observations into a centralized database system. Then the team worked with the trade contractors to perform pre-task planning to identify hazards associated with their work and develop processes to mitigate those hazards.
The Gilbane team also held regular principals safety meetings where Gilbane’s project executive and senior leaders of our trade partners discussed safety practices as it related to the current construction progress. These meetings consisted of a jobsite walkthrough to review what was going well and to identify opportunities for improvement. These principal meetings sent a message to all workers onsite that leadership from all companies were committed to safety.
The UCAN project generated 302 construction jobs and safety was a top priority logging: 117,361 man hours with no lost-time accidents!
- Phase 1: 82,444 man hours
- Phase 2: 34,517 man hours
Project Name:
Walter Payton College Preparatory High School Annex
Submitting Company:
Public Building Commission
Category:
New Construction Chicago Under $55 Million
Project Info Sheet:
Walter Payton College Preparatory High School Annex
Project Description
- 3-story, 49,000-sq-ft annex
- Adds approximately 350 student seats
- 15 total classrooms:
- 10 general classrooms
- Art classroom
- Music room with 3 soundproof practice areas
- Special education classroom:
- kitchenette, washers and dryers
- adjoining resource room
- Driver’s education/health classroom
- Dance studio
- Gymnasium:
- Locker facilities
- Equipment storage
- Adjoining weight and fitness room
- Multipurpose black box theater:
- Theatrical lighting grid
- Soundproofing
- Moveable seating
- Storage
- Administrative office
- Student lounge/café
- Elevator
- Existing Building Renovation:
- Minor interior renovations
- Conversion of existing teacher’s lounge in library room into two offices
- Conversion of existing special education room into a biology lab
- Conversion of existing black box theatre into a typical classroom
- Renovations to existing auditorium
Landscaping
Quality of Construction
The tight, urban location of this public high school brought numerous construction challenges. Using the footprint on the existing lot, the annex’s proposed program narrowly fit across two floors, allowing for the upper level to be occupied by the competition-size gymnasium. By locating this volume on top of the building, it reduces the need for long structural systems to support spaces generally requiring shorter spans. In the end, the efficiency of the top-floor gym proved to be a great design opportunity, offering a volumetric shift expressed differently in exterior material color and appearance.
The PBC implemented a two-phase delivery method, grouping the foundation work into one package and the site development, renovation and vertical construction under a separate package. Since the building was occupied during the renovation work, this phasing was critical. Key components of the project logistics plan were establishing a sequence of work that was the least disruptive to school operations, and defining the areas of contractor access and work while classes were in session. The construction team kept the new annex building completely isolated from the existing school for the duration of the project to keep students safe and to minimize disruption to school activities. Delivery time restrictions were also enforced during the morning and afternoon hours of school days when students were entering and exiting the school.
As an example of this close coordination, the team worked with the school in order to provide street parking for teachers, since the mobilization and laydown space for contractors took over the existing parking lot. The team also consulted CDOT extensively on the site’s perimeter protection, which enabled construction to move forward without any traffic closure.
Construction was based on a fast-track schedule, and environmental remediation and soil capping began once the design hit 60% completion. Due to the poor stability of the soil (typical Chicago fill), the foundation of the legacy building is made up of caissons and grade beams – a time-consuming process that needed to be repeated for the new annex. Once the soil was capped, following extensive coordination with CDOT’s Office of Underground Coordination, the construction team dispatched contractors to drill caissons and install grade beams while the design team worked towards 100% completion.
The site’s restricted size and location also created some difficulties in staging construction. Fortunately, Paschen/Milhouse Joint Venture secured an area under the CTA tracks on the west side of the site to set up contractor trailers, parking and material storage. However, the close proximity of the CTA tracks posed an issue during steel erection. The project team came up with a solution which involved erecting the perimeter steel in a “U” shape; first erecting the steel around the east, south, and then west perimeters of the site, then working out from the middle of the building.
The schedule was especially aggressive given the complexity of the scope and sequencing as well as the need for timely delivery. From design to completion, there also was a high level of cooperation and collaboration between the PBC, the client, the architect of record and the construction team, all of whom worked efficiently and effectively to meet the challenge of the accelerated schedule.
Impact on the Community
The critical capital investments into Walter Payton College Preparatory High School have helped to grow the school’s capacity while ensuring students, many who are community residents, learn in a safe, modern and comfortable environment.
The annex has transformed the school by affording students an opportunity to receive an enriched educational experience through the new art, music and performance spaces while the state-of-the-art gymnasium provides access to quality physical activity.
Many of the school’s interior and exterior amenities are available for community recreational use after hours and on weekends. This new learning environment also represents an example of how great public buildings foster sustainability within the community while serving as a developmental engine for the neighborhood.
The construction of the annex opened the door to the entire business community, whether they are just starting out or already established, so that all Chicago-area companies have the opportunity to grow and succeed. The project provided contracting opportunities to businesses and created jobs for residents of the City of Chicago and those who live in the community areas where the project was built.
As responsible stewards of the public fund, the PBC implements a strong economic sustainability program for each project it takes on. This program includes bid incentives for the employment of apprentices, minority and female workers; community hiring and resident workforce requirements; and contract provisions that require minority- and women-owned business participation.
The three-story, 49,000-square-foot annex project employed 518 workers who earned more than $3.1M in wages and benefits. Thirteen members of the surrounding community worked 1,976 hours on this project, and the project has achieved more than 30% minority- and women-owned business participation as paid to date.
As these numbers illustrate, this project created impactful economic opportunities for the community in which it was developed. It doesn’t stop there: the school’s impact on the community goes beyond economics and supports the environmental health of the larger area as well.
As a developer of public facilities the PBC has developed a uniquely comprehensive approach to environmental stewardship. The PBC’s commitment to sustainable development is integrated into every project the agency manages. For the Payton annex this includes, but is not limited to the diversion of construction waste from landfills; utilization of durable and recycled materials in construction, installation of occupancy light sensors/controls; high-efficiency heating and cooling systems; low flow/low-consumption water fixtures; native and adaptive landscaping and aggressive stormwater management.
With many urban sites located in areas challenged by industrial contamination or neighborhoods suffering from blight, the use of PBC’s environmental guidelines on the Payton annex project has served as a catalyst of positive development, introducing a vital community anchor into the neighborhood.
“Payton gives kids from across the city an opportunity to think big, dream big, realize big.” said Mayor Rahm Emanuel (Chicago Sun-Times: September 5, 2016)
Safety Record
A full-time Safety Manager was on site while steel erection, framing, masonry, roofing, and other major activities were taking place, and PMJV employed an outside safety consultant, Sheffield Safety, to perform monthly safety audits.
Special attention was paid to the fact that the area where work was performed is a busy school in a tight site, and all of the necessary precautions were taken to ensure that students, teachers, and community members were diverted safely away from the construction work. The project managers met with Payton’s principal and staff on a regular basis to coordinate construction work with school activities.
The success of this project’s safety record is especially noteworthy given the accelerated schedule, which required the contractors and their subs to work overtime and on weekends to maintain the fast-paced schedule, ensuring that the new addition opened on time for the 2016/17 school year.